Stellantis Media Site FCA Mack Construction Site by the Numbers Contact: Jodi  Tinson FCA Mack Construction Site by the Numbers Mack assembly site investment: $1.6 billionTotal number of new jobs: 3,850Products: three-row, full-size Jeep® SUV and next-generation Jeep Grand CherokeeTiming: End 2020 Site DetailsTotal pavement: 3,005,000 sq. ft. (~ 53 football fields)Completed to date: 114,960 sq. ft. Total underground piping: 30,100 LFCompleted to date: 7,691 LF Total tons of dirt moved: 485,000 tons or 9,700 trucks Total tons of stone brought to site: 375,000 tons or 7,500 trucks BIW Building (Body Shop)Building size: 646,600 sq. ft. Percent of building uplifted: 95% Demolition: 100% Cleaning and painting: 100% Floor polishing: 90% Lighting replacement: 100% Concrete slab replacement: 100%Light fixtures installed: 1,525 Lineal foot of pipe being installed: 6,370 ft 10 new truck docks General AssemblyBuilding size: 1,053,000 sq. ft. 95% of existing engine equipment has been relocated to Dundee Percent of building uplifted: 10% Demolition: 32% Cleaning and painting: 18% Floor polishing: 11% Lighting replacement: 20% Truss cuts: 14% Truss reinforcements: 18%Light fixtures installed: 3,150 Lineal Foot of Pipe Being Installed: 7,000 ft. 38 new truck docks Paint ShopBuilding size: 790,500 sq. ft.  1st Floor – “0 level” – 411,000 sq. ft. 2nd Floor – “32’ Level” – 275,500 sq. ft. Penthouse – “75’ Level” – 94,500 sq. ft. Sub Station, Paint Mix and Sludge Rooms – 9,500 sq. ft.299 caissons; some 120’ deep11,868 cubic yards of concrete (Foundations)30,000 cubic yards of concrete (Walls/Floors)6,500 tons of structural steel1,800 tons of reinforcing steel in concrete Construction StatisticsTotal construction man-hours to date: 239,313Current 1st shift manpower: 590Current 2nd shift manpower: 85 (8/13/19)