Mack assembly site investment: $1.6 billion
Total number of new jobs: 3,850
Products: three-row, full-size Jeep® SUV and next-generation Jeep Grand Cherokee
Timing: End 2020
Site Details
Total pavement: 3,005,000 sq. ft. (~ 53 football fields)
Completed to date: 114,960 sq. ft.
Total underground piping: 30,100 LF
Completed to date: 7,691 LF
Total tons of dirt moved: 485,000 tons or 9,700 trucks
Total tons of stone brought to site: 375,000 tons or 7,500 trucks
BIW Building (Body Shop)
Building size: 646,600 sq. ft.
Percent of building uplifted: 95%
- Demolition: 100%
- Cleaning and painting: 100%
- Floor polishing: 90%
- Lighting replacement: 100%
- Concrete slab replacement: 100%
Light fixtures installed: 1,525
Lineal foot of pipe being installed: 6,370 ft
10 new truck docks
General Assembly
Building size: 1,053,000 sq. ft.
95% of existing engine equipment has been relocated to Dundee
Percent of building uplifted: 10%
- Demolition: 32%
- Cleaning and painting: 18%
- Floor polishing: 11%
- Lighting replacement: 20%
- Truss cuts: 14%
- Truss reinforcements: 18%
Light fixtures installed: 3,150
Lineal Foot of Pipe Being Installed: 7,000 ft.
38 new truck docks
Paint Shop
Building size: 790,500 sq. ft.
- 1st Floor – “0 level” – 411,000 sq. ft.
- 2nd Floor – “32’ Level” – 275,500 sq. ft.
- Penthouse – “75’ Level” – 94,500 sq. ft.
- Sub Station, Paint Mix and Sludge Rooms – 9,500 sq. ft.
299 caissons; some 120’ deep
11,868 cubic yards of concrete (Foundations)
30,000 cubic yards of concrete (Walls/Floors)
6,500 tons of structural steel
1,800 tons of reinforcing steel in concrete
Construction Statistics
Total construction man-hours to date: 239,313
Current 1st shift manpower: 590
Current 2nd shift manpower: 85
(8/13/19)